The main contractor will close down over the Easter weekend removing all traffic management arrangements on Friday 29 March. There will be no restriction during the Easter weekend from Saturday 30 March until Monday 1 April.
The contractor will then return on Tuesday 2 April to close St Vincent Street in order to carry out a permanent reinstatement to the earlier temporary sett reinstatement.
In addition the road marking sub-contractor will be on site to replace the outstanding road markings in Queen Street and Claypotts Road which will be carried out under traffic control.