A couple of updates from the road
maintenance partnership. I have been asked by residents when the work to resurface
the carriageway in Whinny Brae will be completed as it was scheduled to last
for one week from 31 October. Apparently the delay was due to Scottish Water
having to a repair a water main. This repair has now been completed and the road
maintenance partnership will be back on-site next week to complete.
Work to upgrade the unadopted pavements
in Ardmore Avenue was provisionally programmed to start on Monday 10th October.
I am advised that there was some unforeseen slippage in the unadopted footways programme.
The revised date for starting in Ardmore Avenue is Monday 28 November.