Wednesday 27 September 2017

Flood protection scheme- update

Along with fellow Broughty Ferry councillors I recently received a briefing from council engineers on the flood protection scheme.
 
The scheme is being promoted as studies have demonstrated that large areas of Broughty Ferry are at significant risk of flooding. The estimated costs to residents, businesses and infrastructure should this happen would be in the region of £97 million with 450 properties at risk.  The work had been scheduled to begin this summer but for a number of reasons it has been delayed until next summer.  The following information was provided by the council:
‘The design of the project is still progressing. Engineering challenges and approvals associated with the design solution at Douglas Terrace have required more time than originally envisaged, this has postponed the commencement of the legal process required to allow works to proceed. Dundee City Council are using this additional time to undertake additional consultation with statutory bodies and further surveys, studies and models of the Sand Dunes along the Esplanade. Key dates for the project are now late November for publishing of Notice of Flood Protection Scheme. With a potential start date for works late summer 2018, dependant on the result of the associated legal process.’
You can still view a computer model of the proposed flood protection works on YouTube.