I have been advised that work to
carry out remedial surfacing works to Strathern Road between Claypotts Road and
Ellieslea Road is programmed to commence on Monday 8 December 2014 and will last for approximately two weeks. The
contractor for the works is Tayside Contracts.
It will be carried out in 3
phases with through traffic diverted as follows:
Phase 1 – Strathern Road closed
between Claypotts Road and Victoria Road, with through traffic diverted via
Claypotts Road, Queen Street, Victoria Road and reverse.
Phase 2 – Strathern Road closed
between Victoria Road and Grove Road, with through traffic diverted via
Victoria Road, Dundee Road, Ellieslea Road and reverse.
Phase 3 – Strathern Road closed
between Grove Road and Ellieslea Road, with through traffic diverted via Grove
Road, Albany Road, Ellieslea Road and reverse.