Monday, 7 January 2013

Road disruption- update

The council’s network management team has now provided me with a summary of the programme and timescales for the work in respect of the SSE 33Kv Milton of Craigie cable renewal scheme:
 Preliminary work
 7/1 - 8/1 Set up of temporary site offices in Arbroath Road lay-by (Monymusk Park).
 9/1 - 14/1 Trial holes will be taken in Claypotts Road and Queen Street. This will be done using temporary traffic lights.
 Excavate/duct/reinstate
15/1 - 8/2 Arbroath Road (Kemnay Place to Claypotts Terrace). This work will be done under off peak temporary traffic lights and an eastbound road closure (between Kemnay Place and Gotterstone Avenue).
 4/2 - 12/2 St Vincent Street & Brook Street. This work will be done under road closure.
 11/2 - 18/2 Douglas Road & Kemnay Place. This work will be done under road closure.
 19/2 - 7/3 Claypotts Road. This work will be done under road closure.
 8/3 - 22/3 Queen Street. This work will be done under temporary traffic lights. Adjoining side streets will also be closed at certain points.