Wednesday, 23 April 2014

Bus route diversions

I have been contacted by a number of residents about the diversion routes for the buses during the closure of Queen Street for resurfacing works. There are a lot of stops that won’t get a service; most of these are along Monifieth Road. Notices were due to be in place by today to advise passengers of the diversion. The real time signs at the bus shelters will show ‘bus stop out of use’.

Phase 1 (this Friday to Sunday) will be the most difficult period.  A temporary stop has been provided near Hotel Broughty Ferry and it is anticipated that another one will be provided near to The Cambustay. The number 5 will use Balgillo Road, Ballinard Road, Claypotts Road, West Queen Street, Victoria Road and Strathern Road.

Stagecoach buses will be diverted via Abertay Street, Nursery Road, Forthill Road Balgillo Road Ballinard Road, Victoria Road to Strathern Road (Claypotts Road, West Queen Street/Dundee Road).

From Monday only Stagecoach services will be affected but they will be able to use Fort Street.

Tuesday, 22 April 2014

Move to fortnightly bin collections approved

Two votes were taken at last night’s Environment Committee before the SNP administration eventually got its way and approval was given to make the change to the council’s domestic recycling service, including a move to fortnightly residual waste collections across much of Dundee as outlined in an earlier post.

 I supported a Labour Group amendment that called for full consultation to be undertaken with communities, residents and elected members on the implications of new regulations for the collection of recylcates and residual waste in the city. Speaking in the debate I acknowledged that significant public engagement and education would be carried out prior to the roll out of each phase of the new waste collection regime but what was missing was consultation on the adoption of the actual policy. All the opposition councillors voted for the amendment but it was defeated by the SNP majority.

At the start of the debate I had submitted an amendment that called on the committee to instruct the director of the environment department to prepare a further report with alternative options to improve and expand domestic recycling services within the city but retain a weekly residual waste collection. Most of the people who have contacted me about this matter want to be able to recycle more, particularly food waste, but they are concerned about the implications of grey wheelie bins not being emptied every week.  I didn’t think it was unreasonable to explore this option. Cllr. Fraser MacPherson submitted a very similar amendment so I withdrew my amendment, seconding Cllr. MacPherson’s instead. Again, this amendment was defeated by the SNP majority.

Friday, 18 April 2014

New domestic waste collection strategy

On Monday the council’s environment committee is being asked to approve a new domestic waste collection strategy which has the aim of ensuring compliance with the Waste (Scotland) Regulations 2012 and meeting new targets for recycling which are 60% of household waste by 2020 and 70% of all waste by 2025. Included in the measures being proposed are changing the weekly residual waste (grey wheelie bin) collection to a fortnightly collection.

The strategy will be implemented city wide in six phases over 2 years. A large part of Broughty Ferry is in the first phase which will commence later in 2014.  As part of the implementation an extensive programme of public engagement will be carried out at each implementation stage.

The service that people will receive is a bin for paper, card, metals and plastics that will be collected 2 weekly, a bin for glass that will be collected 4 weekly, a bin for garden waste that will be collected either 2 weekly or 4 weekly depending on the season, a container for food waste that will be collected weekly and the current grey wheelie bin for residual waste will be collected 2 weekly. Flatted properties will receive services appropriate to the housing type with varied collection methods.

I attended a briefing on the proposal given by the director of the environment department and I have asked some questions in advance of Monday’s meeting. While supportive of measures that improve recycling rates I have some concerns about these changes, particularly the loss of the weekly residual waste collection. I would be interested to hear what residents think.

Thursday, 17 April 2014

Queen Street carriageway resurfacing work

I have received notification that carriageway resurfacing work is programmed to commence at Queen Street between Fort Street and St. Vincent Street on Friday 25 April 2014 and will last for approximately 15 days. The contractor for the works is Tayside Contracts. In the interest of public safety road closures will be implemented between Fort Street and St Vincent Street.

The works will be carried out in three phases to minimise disruption to traffic.

Phase 1:- Queen Street/Fort Street junction will be closed for 3 days from Friday 25 April to Sunday 27 April.

Phase 2:- Queen Street from East of Fort Street junction to St Vincent Street will be closed for a further 5 days from Monday 28 April.  Fort Street junction will be open.

Phase 3:- Queen Street from East of Fort Street junction to St Vincent Street will be closed for another 5 days from Tuesday 6 May, again the Fort Street junction will be open during this phase of the works.

It is proposed to have no road closures in place from Saturday 3 May to Monday 5 May.

During Phase 1 vehicular traffic will be diverted via Victoria Road, Ballinard Road, Balgillo Road, Forthill Road, Nursery Road, Abertay Street and reverse.

During Phases 2 and 3 vehicular traffic will be diverted via Fort Street, Nursery Road, Abertay Street and reverse.

Phase 2 and 3 closures will not be implemented until Phase 1 has been completed.

Pedestrian thoroughfare will be maintained throughout the works.

Friday, 11 April 2014

Spring is here

I was out and about today visiting constituents and while I was walking along Balgillo Road the lovely display of roadside daffodils at Muirside Terrace caught my eye, a sure sign that spring has definitely arrived.

Linlathen Road

Local residents have contacted me to ask whether the 40mph speed limit on Linlathen Road could be reduced to 30mph. It is the main access road to two housing areas that have a lot of children walking to school. People also use this route for  going to the Brae riding centre and the neurodisability centre.

I approached the City Development Department about it and I was told that the speed limit on Linlathen Road was approved in 2007. As it had no direct frontage it was considered that a 40mph speed limit was appropriate. A local speed limit review was carried out by the council on all A-class and B-class roads in Dundee in 2011 but apparently as Linlathen Road is an unclassified road it didn't feature in the  review.

I would be interested to hear from other local residents about what they think the speed limit on this road should be.


Wednesday, 9 April 2014

Pothole problem in Balmyle Road

When I was out and about today doing a ward inspection I noticed that two big potholes in Balymle Road still need to be filled.  I have sent a reminder to the roads maintenance partnership.